CPEC Projects Progress Update

# Project Name Progress Update Details
1 Port Qasim Electric Company Coal Fired, 2x660, Sindh
  • Financial Closed (FC) achieved.
  • Civil works on site started in May 2015.
  • Approximately 65% Power Plant and 70% Jetty completed
  • Energization in October 2017.
  • Expected Commercial Operation Date (COD) June 2018.
view details
2 Sahiwal 2x660MW Coal-fired Power Plant, Punjab
  • Civil works on site 95% completed.
  • Planned energization in October 2017.
  • Commercial Operation Date (COD) 25 Dec, 2017.
  • However, project is 06 months ahead of schedule i.e energization in May 2017.
view details
3 Engro thar 4x330MW Coal-fired, Thar, Sindh
  • Financial Closed (FC) achieved in April, 2016.
  • Team mobilized at site.
  • Construction work in progress.
  • Construction of Transmission line-contract awarded. Contractor mobilized
  • Commercial Operation Date (COD) June, 2019
view details
4 Surface mine in Block II of Thar Coal field, 6.5 metric ton per annum (mtpa), Thar Sindh
  • Financial Closed (FC) achieved.
  • IA/EA signed.
  • COD expected 2018/2019
view details
5 Gwadar Coal /LNG / Oil Power Project, Gwadar
  • CCCC has registered with PPIB
  • It was agreed on the proposal of Chinese side to facilitate issuance of LoI by PPIB after submission of bank guarantee and agreements with the view to start work on the project by 31st March, 2017 at the latest
view details
6 HUBCO coal power plant 1X660 MW, Hub Balochistan
  • IA/EA Signed
  • Commercial Operation Date (COD) expected 2018/2019
view details
7 Rahimyar Khan Coal Power Project, Punjab
  • Feasibility in process
view details
8 SSRL Thar Coal Block 1 - 6.5 metric ton per annum(mpta) Thar, Sindh
  • Commercial Operation Date (COD) expected 2018 / 2019
view details
9 SSRL 2×660 MW Mine Mouth Power Plant,Sindh
  • Expected Commercial Operation Date (COD) 2018 / 2019
view details
10 Quaid-e-Azam 1000MW Solar Park, Bahawalpur, Punjab
  • COD of 1st 100MW achieved
  • 2nd and 3rd 100 MW under testing
view details
11 Dawood 50MW wind Farm, Bhambore, Sindh
  • Financial Close (FC) achieved
  • Construction started.
  • Testing in Progress.
  • Commercial Operation Date (COD) Jan, 2017.
view details
12 UEP 100MW wind Farm, Jhimpir, Sindh
  • Construction started.
  • Commercial Operation Date (COD) June, 2017
view details
13 Sachal 50MW Wind Farm, Jhimpir, Sindh
  • Financial Close (FC) achieved.
  • Construction in progress.
  • Commercial Operation Date (COD) June, 2017
view details
14 Suki Kinari Hydro power Station, KPK
  • Financial close attained.
  • Land acquisition award announced on 17th Nov, 2016.
  • Commercial Operation Date (COD) 2020/2021.
view details
15 Karot Hydropower Station, AJK & Punjab
  • Land acquisition award done.
  • Financial Close (FC) 2017.
  • Work initiated through equity – 25% civil works completed.
  • Commercial Operation Date (COD) 2020.
view details
16 Matiari to Lahore Transmission line
  • Feasibility study completed
  • Decision on tariff review petition announced by NEPRA
  • COD expected in 2018 / 2019
  • TSA/IA initialed during 6th JCC
  • China Electric Power Equipment and Technology Company(CET) / State Grid nominated by Chinese side
view details
17 Matiari to Faisalabad Transmission line
  • Feasibility study completed
  • Decision on tariff review petition announced by NEPRA
  • COD expected in 2018 / 2019
  • TSA/IA initialed during 6th JCC
  • China Electric Power Equipment and Technology Company(CET) / State Grid nominated by Chinese side
view details
18 Gaddani Power Park Project (2×660MW)
  • Under Study
view details
19 Gaddani Power Park Project (Jetty + Infrastructure)
  • Under Study
view details
20 HUBCO coal power plant 1X660 MW, Hub Balochistan
  • IA/EA Signed.
  • COD expected 2018/2019.
view details
21 Kohala Hydel Project, AJK
  • Feasibility Study (stage-1) Tariff Announced by NEPRA.
  • Land Acquisition process started.
  • Environmental approval in process.
  • Financial close planned in Dec 2017.
  • Expected Commercial Operation Date (COD) 2023.
view details
22 Pakistan Wind Farm II 2X50 MW(Jhampir, Thatta, Sindh)
  • LOS issued  in August 2016
  • EPA initialed on 30th Nov, 2016
  • Financial Close April 2017
  • COD Sep, 2018
view details
23 Thar mine mouth oracle, Thar Sindh
  • Feasibility stage tariff obtained for coal.
  • Shareholding agreement on new equity partners in process.

  •  
view details
24 Muzaffargarh Coal Power Project, Punjab view details
25 KKH Phase II (Thakot -Havelian Section)
  • Contractor mobilized. Work commenced in September, 2016. To be completed by March, 2020
  • Havelian- Abbotabad-Mansehra (40 KM) section will be completed by May, 2018
view details
26 Peshawar-Karachi Motorway (Multan-Sukkur Section)
  • Contractor mobilized
  • Construction works commenced in August, 2016
view details
27 Expansion and reconstruction of existing Line ML-1
  • Feasibility completed
  • Request for Chinese financing submitted on 29th Nov, 2016
  • Senior Officials to discuss and finalize modalities/terms of financing
  • Both side agreed to have extensive communication in the first fortnight of Jan, 2017 to reach consensus within three months
view details
28 Havelian Dry port (450 M. Twenty-Foot Equivalent Units)
  • Feasibility completed
  • Request for Chinese financing submitted on 29th Nov, 2016
view details
29 Gwadar East-Bay Expressway
  • Minutes of EAD-MOFCOM signed
view details
30 New Gwadar International Airport
  • Minutes of EAD-MOFCOM signed in August 2016
  • Grant request is being processed by Chinese Side
view details
31 Construction of Breakwaters
  • Draft business plan has been received from Chinese (COPHCL), under review by MoP&S and GPA 
view details
32 Dredging of berthing areas & channels
  • Draft business plan has been received from Chinese (COPHCL), under review by MoP&S and GPA
view details
33 Development of Free Zone
  • Tax exemptions for port and Free Zone notified in Finance Bill 2016
  • Ground breaking done by the Prime Minister
  • 100% private Investment inside Free Zone. To be operated by COPHCL
  • 1st phase completion date is December 2017
  • Significant progress and response from investors
  • Gwadar Free Zone investment guide line published
view details
34 Necessary facilities of fresh water treatment, water supply and distribution
  • PC-I for 5 MGD RO plant for Gwadar cleared by CDWP in Dec 2016
  • Draft Framework Agreement shared with Chinese side and likely to be signed soon
view details
35 Pak China Friendship Hospital
  • Grant  request  sent by EAD to MOFCOM
  • Feasibility study completed by Chinese team to add 100 beds from existing 50, for subsequent extension to 300 beds
  • LOE is expected to be signed in early 2017
view details
36 Technical and Vocational Institute at Gwadar
  • Chinese technical team expected to visit early this year to conduct feasibility study
  • MoU likely to be signed soon
view details
37 Cross Border Optical Fiber Cable
  • Ground breaking cermony performed by the Prime Minister
  • Work commenced October 2015
    Work on 220km/ 820km segment completed
view details
38 Pilot Project of Digital Terrestrial Multimedia Broadcast (DTMB)
  • Project completed at a cost of US$ 2 million
  • As confirmed by Mo I &B LoE on demonstration project with Chinese side is being processed

 

view details
39 Karachi Circular Railway
  • JCC agreed in principle for inclusion of Rail Based Mass Transit Systems in Provincial headquarters as part of CPEC
  • JWG on Transport Infrastructure has been asked to complete the necessary formalities
view details
40 Greater Peshawar Region Mass Transit
  • JCC agreed in principle for inclusion of Rail Based Mass Transit Systems in Provincial headquarters as part of CPEC
  • JWG on Transport Infrastructure has been asked to complete the necessary formalities
view details
41 Quetta Mass Transit
  • JCC agreed in principle for inclusion of Rail Based Mass Transit Systems in Provincial headquarters as part of CPEC
  • JWG on Transport Infrastructure has been asked to complete the necessary formalities
view details
42 Orange Line - Lahore view details
43 Keti Bunder Sea Port Development Project
  • Further studies and consultations to be initiated
  • Projects referred to concerned JWGs for consideration
view details
44 Naukundi-Mashkhel-Panjgur Road Project connecting with M-8 & N-85
  • Further studies and consultations to be initiated
  • Projects referred to concerned JWGs for consideration
view details
45 Chitral CPEC link road from Gilgit, Shandor, Chitral to Chakdara
  • Further studies and consultations to be initiated
  • Projects referred to concerned JWGs for consideration
view details
46 Mirpur – Muzaffarabad - Mansehra Road Construction for connectivity with CPEC route
  • Further studies and consultations to be initiated
  • Projects referred to concerned JWGs for consideration
view details
47 Quetta Water Supply Scheme from Pat feeder Canal, Balochistan
  • Relevant Provincial Govts. to work out proposals on implementation of projects
view details
48 Iron Ore Mining, Processing & Steel Mills complex at Chiniot, Punjab
  • Relevant Provincial Govts. to work out proposals on implementation of projects
view details
49 Rashakai Economic Zone on M-1
  • Work on SEZs to be initiated on priority
view details
50 Special Economic Zone Dhabeji
  • Work on SEZs to be initiated on priority
view details
51 Bostan Industrial Zone
  • Work on SEZs to be initiated on priority
view details
52 Punjab - China Economic Zone, M-2 District Sheikhupura
  • Work on SEZs to be initiated on priority
view details
53 ICT Model Industrial Zone, Islamabad
  • Work on SEZs to be initiated on priority
view details
54 Development of Industrial Park on Pakistan Steel Mills Land at Port Qasim near Karachi
  • Work on SEZs to be initiated on priority
view details
55 Bhimber Industrial Zone
  • Work on SEZs to be initiated on priority
view details
56 Mohmand Marble City
  • Work on SEZs to be initiated on priority
view details
57 People to People exchanges
  • Efforts for intensification of People to People contact, media and cultural exchanges (including movies, drama, theatre etc.) would be done through agreed yearly programmes. Both sides resolved to promote Chinese and Pakistani culture and heritage as a way of long term partnership
view details
58 Transfer of Knowledge in different sectors
  • Experts from Industrial zones, rural and urban development, job creation & SMEs, water resources management & treatment and  agriculture
view details
59 Gwadar Smart Port City Master Plan
  • LOE signed in August 2016
  • Name of one Consultant received by EAD. The case is being processed on fast track to ensure completion within twelve months
view details
60 Bao Steel Park, petrochemicals, stainless steel and other industries in Gwadar
  • Necessary approval process would be completed at the earliest for inclusion as new CPEC Project under Gwadar JWG
view details
61 Development of Gwadar University (Social Sector Development)
  • Chinese side will identify a leading Chinese university for collaboration with University of Gwadar on marine & maritime related subjects along with other disciplines
view details
62 Upgradation and development of fishing, boat making and maintenance services to protect and promote livelihoods of local population
  • COPHCL would take effective measures for social sector development 
view details
63 Moqpondass SEZ Gilgit-Baltistan
  • Work on SEZs to be initiated on priority
view details
64 Khuzdar-Basima Road N-30 (110 km)
  • Procedural formalities to be completed shortly
view details
65 Upgradation of D.I.Khan - Zhob, N-50 Phase-I (210 km)
  • Procedural formalities to be completed shortly
view details
66 KKH Thakot-Raikot N35 remaining portion (136 Km)
  • Procedural formalities to be completed shortly
view details
67 Capacity Development of Pakistan Railways
  • Focus groups be established for effective training and capacity enhancement
view details