Expansion and reconstruction of existing Line ML-1

Project Expansion and reconstruction of existing Line ML-1
Project Description

Project Title: Rehabilitation & Up-gradation of Karachi-Lahore Peshawar (ML-1) Railway Track (1,872 kms)

Scope:

  • Doubling of entire track from Karachi to Peshawar
  • Speed of passenger trains to be raise from 65/110km/h to 160 km/h
  • Freight trains to operate at 120 km/h
  • Computer based signaling and control system
  • Grade separation to ensure safety of train operations

Responsibility:

  • Proposing Agency: Ministry of Railways
  • Implementing Agency: Pakistan Railways
  • Supervising Agency: Ministry of Communications, Government of Pakistan
Location Karachi to Peshawar via Hyderabad, Nawabshah, Rohri, RahimyarKhan, Bahawalpur, Khanewal, Sahiwal, Lahore, Gujrawala, Rwalpindi, Peshwar
Estimated Cost (US $ Million) 8,172
Financing Work will be carried out by financing possibly through Chinese Government Concessional Loan (GCL). Work will be awarded through open bidding as per PPRA rules through EPC contract
Project Progress Update
  • Feasibility completed
  • ML-1 Project declared ‘Strategic’ by 6th JCC in Beijing
  • Framework Agreement on ML-1 signed on 15th May 2017 during PM Visit to China
  • Commercial Contract for Preliminary Design signed on 15th May, 2017
  • Project will be completed in 2 phases
  • PC-1 of Phase-1 approved by CDWP in May 2018​
  • Expected COD 2022