Upgradation of D.I.Khan (Yarik) - Zhob, N-50 Phase-I (210 km)

Project Upgradation of D.I.Khan (Yarik) - Zhob, N-50 Phase-I (210 km)
Project Description

Salient Features of the Project:

  • On existing alignment (section of N-50) with geometric improvements
  • 210 km in length. Improvement / Upgradation of 2 lane existing road to 4 lane. 100m R.O.W will be acquired to upgrade it to 6 lanes in future

Estimated Cost:

  • Total (Construction plus land acquisition): Rs.76,486 million

 

Province Khyber Pakhtunkhwa - Balochistan
Executing Company / Sponsors National Highway Authority
Supervising Agency Ministry of Communications
Project Progress Update
  • PC-I Approved by ECNEC on 12th April, 2017.
  • Land acquisition in Progress.
  • Accorded highest priority in 8th JCC

 