CPHGC 1,320MW Coal-fired Power Plant, Hub,Balochistan

Project CPHGC 1,320MW Coal-fired Power Plant, Hub,Balochistan
Primary Energy Input Coal (Imported)
Technology Super Critical
Installed Capacity (MW) 1320
Location Hub
Province Baluchistan
Estimated Cost (US $ Million) 1940
Executing Company / Sponsors China Power Hub Generation Company (Private) Limited
Financing Independent Power Producer (IPP)
Coordinating Ministry Ministry of Water and Power
Supervising Agency Private Power and Infrastructure Board (PPIB)
Project Progress Update
  • IA signed on 25th January 2017
  • LOS issued on 12th April 2016; 1st extension to LOS issued on 24th January 2017

 

  • Commercial Operation Date (COD) expected 2018/2019