Salient Features of the Project:
- On existing alignment (section of N-50) with geometric improvements
- 331 km in length. Existing 2 lanes are in very good condition. Addition of 2 new lanes for dualization of Existing N-50 to 4 lane. Geometric improvements will be made to the existing alignment to achieve the design speed. 100m R.O.W will be acquired to upgrade it to 6 lanes in future.
Estimated Cost:
- Construction: Rs.63,601 million
- Land Acquisition, properties compensation and shifting of utilities: Rs.3,232 million
- Total: Rs.66,833 million
|