Azad Pattan Hydel Project, AJK

Project Azad Pattan Hydel Project, AJK
Primary Energy Input Hydel
Installed Capacity (MW) 701
Location Jhelum River
Estimated Cost (US $ Million) 1,650
Executing Company / Sponsors China Gezhouba Group/ Larab Group
Financing Independent Power Producer (IPP)
Coordinating Ministry Ministry of Energy (Power Division)
Supervising Agency Private Power and Infrastructure Board (PPIB)
Project Progress Update
  • LoI and LoS issued
  • Agreement signed on 6th July 2020
  • Expected commercial operation date (COD) 2026