Sachal 50MW Wind Farm (Jhimpir, Thatta)

Project Sachal 50MW Wind Farm (Jhimpir, Thatta)
Primary Energy Input Wind
Technology Wind Turbine
Installed Capacity (MW) 50
Tariff Cost + Tariff (US cnt/kw 15.8618)
Location Jhimpir, District Thatta
Province Sindh
Estimated Cost (US $ Million) 134
Executing Company / Sponsors Hydro China / Arif Habib Corporation Limited
Financing Independent Power Producer (IPP)
Coordinating Ministry Ministry of Water and Power
Supervising Agency Alternative Energy Development Board (AEDB)
Project Progress Update
  • Financial Closed (FC) achieved on December 18, 2015.
  • Commercial Operation Date (COD) attained 11 April, 2017.
  • Current Status: Operational.