Hydro China Dawood 50MW Wind Farm(Gharo, Thatta)

Project Hydro China Dawood 50MW Wind Farm(Gharo, Thatta)
Primary Energy Input Wind
Technology Wind Turbine
Installed Capacity (MW) 50
Tariff Upfront Tariff
Location Bhanbore, Gharo, District Thatta
Province Sindh
Estimated Cost (US $ Million) 125
Executing Company / Sponsors M/s Hydrochina Dawood Power Pvt. Limited (HDPPL)
Financing Independent Power Producer (IPP)
Coordinating Ministry Ministry of Water and Power
Supervising Agency Alternative Energy Development Board (AEDB)
Project Progress Update
  • Financial Closed (FC) achieved on March 27, 2015.
  • Commercial Operation Date (COD) attained 5th April, 2017.
  • Current Status: Operational.

Picture Gallery