Hydro China Dawood Wind Farm(Gharo, Thatta)

Project Hydro China Dawood Wind Farm(Gharo, Thatta)
Primary Energy Input Wind
Technology Wind Turbine
Installed Capacity (MW) 49.5
Tariff Upfront Tariff
Location Bhanbore, Gharo, District Thatta
Province Sindh
Estimated Cost (US $ Million) 112.65
Executing Company / Sponsors Hydrochina Dawood Power Pvt. Limited (HDPPL)
Financing Independent Power Producer (IPP)
Coordinating Ministry Ministry of Water and Power
Supervising Agency Alternative Energy Development Board (AEDB)
Project Progress Update
  • Financial Closed (FC) achieved on March 27, 2015
  • Commercial Operation Date (COD) attained 5th April, 2017
  • Current Status: Operational 