Engro Thar Block II 2×330MW Coal fired Power Plant
TEL 1×330MW Mine Mouth Lignite Fired Power Project at Thar Block-II, Sindh, Pakistan
ThalNova 1×330MW Mine Mouth Lignite Fired Power Project at Thar Block-II, Sindh, Pakistan

Project Engro Thar Block II 2×330MW Coal fired Power Plant
TEL 1×330MW Mine Mouth Lignite Fired Power Project at Thar Block-II, Sindh, Pakistan
ThalNova 1×330MW Mine Mouth Lignite Fired Power Project at Thar Block-II, Sindh, Pakistan
Primary Energy Input Coal (Local)
Technology Sub Critical
Installed Capacity (MW) 660
330

330
Location Thar-Block-II
Province Sindh
Estimated Cost (US $ Million) 2,000
Executing Company / Sponsors Engro Power Gen Thar LTd. / China Machinery Engineering Corporation (CMEC)
Financing Independent Power Producer (IPP)
Coordinating Ministry Ministry of Water and Power
Supervising Agency Private Power and Infrastructure Board (PPIB)
Project Progress Update
  • Financial Closed (FC) achieved in April, 2016.
  • Team mobilized at site.
  • Construction work in progress.
  • Construction of Transmission line-contract awarded. Contractor mobilized
  • Commercial Operation Date (COD) June, 2019