1000MW Quaid-e-Azam Solar Park (Bahawalpur)

Project 1000MW Quaid-e-Azam Solar Park (Bahawalpur)
Primary Energy Input Solar
Technology PV Solar
Installed Capacity (MW) 400 / 600
Location Bahawalpur, Punjab
Province Punjab
Estimated Cost (US $ Million) 520 / 781
Executing Company / Sponsors Zonergy
Financing Independent Power Producer (IPP)
Coordinating Ministry Ministry of Energy (Power Division)
Supervising Agency Punjab Power Development Board (PPDB) / Alternative Energy Development Board (AEDB)
Total Jobs Created 231
Total Local Jobs Created 220
Total Jobs Created During the Construction of this Project 1200
Project Progress Update
• 400 MW project completed in August 2016.
600MW under Implementation.

Picture Gallery