1320MW Sahiwal Coal-fired Power Plant

Project 1320MW Sahiwal Coal-fired Power Plant
Primary Energy Input Coal (Imported)
Technology Super Critical
Installed Capacity (MW) 1320
Location Qadarabad, Sahiwal
Province Punjab
Estimated Cost (US $ Million) 1912.2
Executing Company / Sponsors Huaneng Shandong Rui Group, China
Financing Independent Power Producer (IPP)
Coordinating Ministry Ministry of Energy (Power Division)
Supervising Agency Private Power and Infrastructure Board (PPIB) / Punjab Power Development Board (PPDB)
Total Jobs Created 1683
Total Local Jobs Created 1033
Total Jobs Created During the Construction of this Project 3770
Project Progress Update
  • Project Completed on 28th October 2017.
  • Current Status: Operational.

Picture Gallery