D.I Khan (Yarik) –Zhob (N-50)

Project D.I Khan (Yarik) –Zhob (N-50)
Length (KM) 210
Project Description

Salient Features of the Project:

  • On existing alignment (section of N-50) with geometric improvements
  • 210 km in length. Improvement / Upgradation of 2 lane existing road to 4 lane. 100m R.O.W will be acquired to upgrade it to 6 lanes in future. 

Estimated Cost:

  • Total (Construction plus land acquisition): Rs.76,486 million
Project Progress Update
  • PC-I Approved by ECNEC on 12th April, 2017
  • Land acquisition in Progress
  • Accorded highest priority in 9th JCC