330MW HUBCO Thar Coal Power Project (Thar Energy)

Project 330MW HUBCO Thar Coal Power Project (Thar Energy)
Primary Energy Input Thar Coal
Technology Sub Critical
Installed Capacity (MW) 330
Location Thar Block - II
Province Sindh
Estimated Cost (US $ Million) 497.70
Executing Company / Sponsors HUBCO, FFC, China Machinery Engineering Corporation (CMEC)
Financing Independent Power Producer (IPP)
Coordinating Ministry Ministry of Energy (Power Division)
Supervising Agency Private Power and Infrastructure Board (PPIB)
Total Jobs Created During the Construction of this Project 805
Project Progress Update
  • Financial Close (FC) achieved on 30th Jan 2020.
  • Project Completed on 30th September 2022.
  • Current Status: Operational