CPEC Projects Progress Update

Energy Projects Under CPEC

# Project Name Progress Update Pictures Details
Completed Projects
1 1320MW Sahiwal Coal-fired Power Plant
  • Project Completed on 28th October 2017.
  • Current Status: Operational.
1320MW Sahiwal Coal-fired Power Plant view details
2 1320MW Coal-fired Power Plant at Port Qasim Karachi
  • Project completed on 25th April 2018.
  • Current Status: Operational
1320MW Coal-fired Power Plant at Port Qasim Karachi view details
3 1320MW China Hub Coal Power Project, Hub Balochistan
  • Project completed on 17th Aug 2019.
  • Current Status: Operational
  • Video: 

 

 

1320MW China Hub Coal Power Project, Hub Balochistan view details
4 660MW Engro Thar Coal Power Project
  • Project completed on 10th July 2019.
  • Current Status: Operational
660MW Engro Thar Coal Power Project view details
5 1000MW Quaid-e-Azam Solar Park (Bahawalpur)
• 400 MW project completed in August 2016.
600MW under Implementation.
1000MW Quaid-e-Azam Solar Park (Bahawalpur) view details
6 50 MW Hydro China Dawood Wind Farm, Gharo, Thatta
  • Project completed on 5th April 2017.
  • Current Status: Operational.
50 MW Hydro China Dawood Wind Farm, Gharo, Thatta view details
7 100MW UEP Wind Farm, Jhimpir, Thatta
  • Project completed on16th June 2017.
  • Current Status: Operational
100MW UEP Wind Farm, Jhimpir, Thatta view details
8 50MW Sachal Wind Farm ,Jhimpir, Thatta
  • Project completed on 11 April 2017.
  • Current Status: Operational 
50MW Sachal Wind Farm ,Jhimpir, Thatta view details
9 100MW Three Gorges Second and Third Wind Power Project
  • Second Wind Farm completed on 30th June 2018.
  • Third Wind Farm completed on 9th July 2018.
  • Current Status: Operational.
100MW Three Gorges Second and Third Wind Power Project view details
10 Matiari to Lahore ±660 KV HVDC Transmission Line Project
  • Project completed on 1st September 2021.
  • Current Status: Operational.
Matiari to Lahore ±660 KV HVDC Transmission Line Project view details
11 720MW Karot Hydropower Project, AJK/Punjab
  • Financial Close (FC) achieved in March 2017.
  • Project Completed on 29th June 2022.
  • Current Status: Operational
720MW Karot Hydropower Project, AJK/Punjab view details
12 330MW HUBCO Thar Coal Power Project (Thar Energy)
  • Financial Close (FC) achieved on 30th Jan 2020.
  • Project Completed on 30th September 2022.
  • Current Status: Operational
330MW HUBCO Thar Coal Power Project (Thar Energy) view details
13 1320MW SSRL Thar Coal Block-I 7.8 mtpa & Power Plant (2×660MW) (Shanghai Electric)
  • Mine Financial Close (FC) achieved on 30th Dec 2019.
  • GoS-WUA signed on 25th February 2021.
  • Project Completed on 5th February 2023.
  • Current Status: Operational.
1320MW SSRL Thar Coal Block-I 7.8 mtpa & Power Plant (2×660MW) (Shanghai Electric) view details
14 330MW HUBCO ThalNova Thar Coal Power Project
  • Financial Close (FC) achieved on 30th September 2020.
  • Project Completed on 17th February 2023.
  • Current Status: Operational.
330MW HUBCO ThalNova Thar Coal Power Project view details
Under Construction Projects
15 884MW Suki Kinari Hydropower Project, KP
  • Financial Close (FC) achieved in Feb 2017
  • 70% work completed.
884MW Suki Kinari Hydropower Project, KP view details
16 300MW Coal-Fired Power Project at Gwadar
  • Tariff determined in Sep 2019.
  • Land acquired in Feb 2020.
  • GoP-IA and PPA signed on 8th April 2021.
  • Financial Close (FC) under process.
300MW Coal-Fired Power Project at Gwadar view details
Under Consideration Projects
17 1124MW Kohala Hydropower Project, AJK
  • Land Acquisition process started.
  • TPA, TPPA and GoP-IA signed on 25th June 2020.
  • GoAJK-IA and GoAJK-WUA signed in April 2021.
  • Financial Close (FC) under progress.
1124MW Kohala Hydropower Project, AJK view details
18 700.7MW Azad Pattan Hydropower Project, AJK/Punjab
  • Land Acquisition process started.
  • TPPA, GoP-IA, and GoPb-WUA Signed in July 2020.
  • GoAJK-IA and GoAJK-WUA signed in December 2020.
  • Financial Close (FC) under progress.
700.7MW Azad Pattan Hydropower Project, AJK/Punjab view details
19 1320 MW Thar Mine Mouth Oracle Power Plant & surface mine
  • LoI stage
view details
20 50MW Cacho Wind Power Project
  • LOI Stage
view details
21 50MW Western Energy (Pvt.) Ltd. Wind Power Project
  • LOI stage

 

view details

Transport Infrastructure Projects under CPEC

# Project Name Progress Update Pictures Details
Completed Projects
1 KKH Phase II (Havelian - Thakot Section)
  • Work commenced in September 2016.
  • Havelian - Mansehra Section Inaugurated by Prime Minister on 18th November 2019.
  • Mansehra - Thakot Section Inaugurated by CM KPK on 28th July 2020.

 

KKH Phase II (Havelian - Thakot Section) view details
2 Peshawar-Karachi Motorway (Multan-Sukkur Section)
  • Construction work commenced in August 2016.
  • Project Completed and inaugurated on 05 November 2019.
Peshawar-Karachi Motorway (Multan-Sukkur Section) view details
3 Orange Line Metro Train - Lahore
  • Project completed and inaugurated on 25th October 2020.
Orange Line Metro Train - Lahore view details
4 Cross Border Optical Fiber Cable (Khunjrab - Rawalpindi)
  • Groundbreaking did by the Prime Minister.
  • Work commenced in October 2015.
  • Project Completed and inaugurated by Prime Minister in July 2018.
Cross Border Optical Fiber Cable (Khunjrab - Rawalpindi) view details
5 Pilot Project of Digital Terrestrial Multimedia Broadcast (DTMB)
  • Pilot Project inaugurated in April 2015.

 

view details
6 Hakla - D.I Khan Motorway
  • ECNEC approved separate PC-Is for construction and land acquisition on 07-11-2016.
  • Project completed and inaugurated on 05 January 2022.
Hakla - D.I Khan Motorway view details
Under Construction Projects
7 Zhob - Quetta (Kuchlak) (N-50)
  • ECNEC approved separate PC-Is for construction and land acquisition of the project on 28-03-2019.
  • Prime Minister did the groundbreaking on 29th March 2019.
  • Tendering for construction work of two sections is completed and contractor mobilized whereas the remaining three sections tendering will process soon.
view details
8 Khuzdar-Basima Road (N-30)
  • PC-I has been approved by ECNEC on 12-04-2017.
  • Work started: October 2019.
  • The project Basima-Khuzdar has been taken up through PSDP.
  • 99% physical work completed.
  • Expected completion date is 31st July 2023.
Khuzdar-Basima Road (N-30) view details
9 Hoshab - Awaran Road Section (M-8)
  • Tendering for construction work of is completed and contractor mobilized in June 2021.
view details
10 KKH Alternate Route Shandur - Chitral Road
  • Groundbreaking performed by Prime Minister in April 2021.
view details
11 Nokundi-Mashkhel Road
  • Prime Minister did groundbreaking on 20th May 2021.
  • Tendering for construction work of is completed and contractor mobilized.
view details
In-Pipeline Projects
12 Up-gradation and Dualization of ML-1 and establishment of Dry Port near Havelian
  • Feasibility completed.
  • ML-1 Project declared 'Strategic' by 6th JCC in Beijing.
  • Framework Agreement on ML-1 signed on 15th May 2017 during PM Visit to China.
  • Commercial Contract for Preliminary Design signed on 15th May 2017.
  • Project will be completed in 3 packages.
  • PC-1 approved by ECNEC on 5th August 2020.
  • Both countries constituted Financing Committee to finalize the concessional financing agreement. 
view details
13 Up-gradation of D.I.Khan (Yarik) - Zhob, N-50 Phase-I
  • PC-I Approved by ECNEC on 12th April 2017.
  • Land acquisition in Progress.
  • The project is on the highest priority and under negotiation with the Chinese side.
  • Financial negotiation is under process.
Up-gradation of D.I.Khan (Yarik) - Zhob, N-50 Phase-I view details
14 KKH Alternative Route Gilgit-Shandur Road
  • PC-I approved with a cost of Rs 49.9 billion dated 4.6.2021. 
  • Procurement in process and will be finalized by Oct 2021.
view details
15 Realignment of KKH Phase-I Thakot - Raikot Section
  • G-to-G technical working group has been constituted for the re-alignment of KKH Phase-I Thakot – Raikot Section
view details
16 Peshawar - D.I.Khan Motorway
  • PC-I by ECNEC with a cost of Rs 276 billion.
  • The project will be further discussed in next JWG meeting.
view details
17 Awaran - Khuzdar Road Section (M-8)
  • PC-I approved with a cost of Rs 32 billion dated 26.5.2021.
  • Technical bid evaluation is in process and procurement will be finalized by Nov 2021.
view details
18 Dir Expressway
  • PC-I approved ECNEC with a cost of Rs 38.9 billion.
  • The project will be further discussed in next JWG meeting.
view details
19 DTMB-A (Digitalize the existing three sites of PTV)
  • The signing of revised LoE and IA is under process.
view details
Long Term Projects
20 Mirpur-Muzaffarabad-Mansehra Road
  • PC-I is under approval process.
view details
21 Karachi Circular Railway
  • The project will be built in PPP mode. The Transaction Advisory is under process in P3A.  
view details
22 Mashkhel - Pangur Road
  • Detail design and feasibility are under process.
view details
23 Quetta Mass Transit
  • Detail design and feasibility are under process.
view details
24 Greater Peshawar Region Mass Transit
  • Detail design and feasibility are under process.
view details

Gwadar Projects Under CPEC

# Project Name Progress Update Pictures Details
Completed Projects
1 Development of Port and Free Zone
  • Tax exemptions for port and Free Zone notified in Finance Act 2020
  • 1st phase (60 acres) completed
  • 46 enterprises have been registered for investment in Free Zone.
  • 03 companies started production
  • First imports cum exports cargo by M/s HKSUN received in Gwadar free zone on 7th April 2021.
  • Development of 2nd phase (2,221 acres) started in July, 2021.

 

Development of Port and Free Zone view details
2 Gwadar Smart Port City Master Plan
  • Completed and approved by the governing body of GDA & ratify by the JCC in its 9th meeting held on 5th November 2019.
  • Micro-Land use planning and Governance Model is under process with Gwadar Development Authority.
  • The Govt. of Balochistan approved & enacted tax exemptions for Gwadar city. 
view details
3 Pak-China Technical and Vocational Institute at Gwadar
  • Groundbreaking held on 16th December 2019.
  • Project completed and inaugurated on 30th September 2021.
  • The institute had operationalized with induction of students for short courses (3-6 months).
Pak-China Technical and Vocational Institute at Gwadar view details
4 Gwadar Eastbay Expressway
  • Cost approved by ECNEC on 12-01-2015
  • Contract Agreement was signed b/w GPA & CCCC on 24-09-2017
  • The groundbreaking ceremony of Eastbay Expressway was held on 22nd November 2017 by Prime Minister
  • Eastbay Expressway Gwadar: 19km (14.5 offshore completed & 4.5 onshore under construction.)
  • Project completed and inaugurated on 3rd June 2022.
Gwadar Eastbay Expressway view details
5 Pak-China Friendship Hospital
  • Groundbreaking held on 16th Dec 2019.
  • Civil work started by November 2020.
  • The project is successfully completed and inaugurated by the Honorable Prime Minister of Pakistan during his visit to Gwadar on 04th December, 2023
Pak-China Friendship Hospital view details
6 1.2 MGD Desalination Plant
  • Project Implementation Agreement signed on 5th July 2021.
  • 85% of civil work is completed. 
  • China-Aid Gwadar seawater desalination project Mid-term inspection has been completed.
  • The project is successfully completed and inaugurated by the Honorable Prime Minister of Pakistan during his visit to Gwadar on 04th December, 2023

 

view details
Under Construction Projects
7 New Gwadar International Airport
  • Groundbreaking held by Prime Minister on 29th March 2019.
  • Construction work started on 31st October 2019.
  • Expected completion date: June 2024.
New Gwadar International Airport view details
8 Necessary facilities of fresh water treatment, water supply and distribution
  • Phase-1, lying of pipelines from Swad Dam to Gwadar has been completed.
  • Phase-II laying an additional pipeline from Shadi Khau Dam to Swad Dam has also been completed.
  • Total of 158km pipeline, constructed to channel water from the Shadi Kor and Swad dams. Which has successfully resolved the water scarcity issue for the residents of Gwadar town.
  • Phase-III, Up-gradation of the water distribution system of Gwadar city is under way around 141 km new water distribution pipeline has been installed to ensure every household in the city has access to drinking water.
Necessary facilities of fresh water treatment, water supply and distribution view details
9 300MW Coal-Fired Power Project at Gwadar
  • Tariff determined in Sep 2019.
  • Land acquired in Feb 2020.
  • GoP-IA and PPA signed on 8th April 2021.
  • Financial Close (FC) under process.
300MW Coal-Fired Power Project at Gwadar view details
10 5 MGD Water Desalination Plant Gwadar
  • The project PC-1 approved by ECNEC in 2018.
  • Tendering under process.
view details
In-Pipeline Projects
11 Construction of Breakwaters
  • Joint feasibility study completed.
  • Preparation of PC-1 under process with Ministry of Maritime Affairs.

 

view details
12 Dredging of berthing areas & channels
  • Project feasibility study has been completed in June, 2023.
  • Preparation of PC-1 under process with Ministry of Maritime Affairs
view details
13 Fish Landing Jetty and Fishermen Boat Making Industry on West bay
  • Project agreed in 7th JCC.
  • Pakistani side proposed grant funding.
  • Feasibility study completed and shared with the Chinese side through EAD.
view details
14 Gwadar Smart Environment Sanitation System and Landfill Project
  • Project agreed in 7th JCC. 
  • Pakistani side proposed grant funding.
  • PC-1 approved by CDWP and Grant application submitted to EAD, which was forwarded to MOFCOM through the Chinese Embassy.
view details

Industrial Cooperation/Special Economic Zones(SEZs)

# Project Name Progress Update Pictures Details
Under Construction Projects
1 Rashakai Special Economic Zone
  • Concession Agreement between Khyber Pakhtunkhwa Economic Zone Development and Management Company (KPEZDMC) and China Road & Bridge Corporation (CRBC) was signed in April 2019.
  • The development agreement was signed on 14 Sep 2020 with a development cost of $128 million.
  • Groundbreaking / launching of RSEZ was held on 28th May 2021.
  • Phase-I (247 acres) has been developed and launched for investments. Numerous enterprises have been registered whereas few have started construction of their industrial units.

 

Rashakai Special Economic Zone view details
2 Allama Iqbal Industrial City
  • Groundbreaking of AIIC was held on 3rd January 2020 which was attended by the Prime Minister of Pakistan and development work is in progress.
  • Numerous national and international enterprises have been allotted plots in the SEZ. Few companies have already started construction of their industrial units and expected to initiate operations soon.
Allama Iqbal Industrial City view details
3 Dhabeji Special Economic Zone
  • Concession Agreement was signed on 25th February 2022.
  • Groundbreaking of Dhabeji SEZ was held on 15th July 2023 and development work is in progress.
  • Utilities are being provided at the door step of the zone.
view details
4 Bostan Special Economic Zone
  • The SEZ Approval Committee officially approved the Bostan SEZ on 4th March 2020 in the 5th Board of Approval meeting and awarded SEZ status on 5th May, 2020.
  • Development work on phase-I (200 acres) has been completed.
  • Phase-1 of Bostan SEZ has been launched for allotment of industrial plots.

 

Bostan Special Economic Zone view details
In-Pipeline Projects
5 ICT Model Industrial Zone view details
6 Industrial Park on Pakistan Steel Mill Land view details
7 Mirpur Industrial Zone view details
8 Mohmand Marble City view details
9 Moqpondass Special Economic Zone view details

Social and Economic Development under CPEC

# Project Name
Completed Projects
1 Provision of Vaccine storage and transportation equipment to NDMA
2 Poverty Alleviation Training
3 Emergency relief supplies for enhancing NDMA, disaster preparedness capacity
4 Pakistan Vocational and Technical Education Capacity build-up project
5 Pakistan Vocational Schools equipment Upgrading and Renovation Project
6 Provision of Medical equipment and materials
7 Gwadar hospital project
8 Gwadar Desalination Plant
9 Gwadar Vocational and Technical Project
10 Drinking water equipment
Under Construction Projects
11 China-Pakistan Joint Agricultural Technology Laboratory
12 Provision of Agricultural equipment and tools
13 Establishment of 50-Smart Classroom for Higher education in Pakistan
14 Maintenance and renovation for 50 schools in newly merged districts
15 Provision of 20, 000 Overseas student scholarship
16 China-Pakistan Joint Agricultural demonstrations
17 Establishment of Burn Centres in Punjab, Khyber Pakhtunkhwa, Balochistan, AJK and Gilgit Baltistan.
18 10,000 Solar-powered lighting equipment for Balochistan
19 Medical Emergency center in Quetta, Balochistan
20 Cooperative Project with Pak-Austria Fachhochule: Institute of Applied Sciences and Technology
In-Pipeline Projects
21 Bacterial grass (JunCao) Technology Training and promotion project
22 Brightness journey in Pakistan
23 Pakistan Agricultural Vocational Training
24 Provision of teaching equipment for primary and secondary schools
25 China-Pak joint telemedicine network
26 Rural poverty reduction joint research project
27 Punjab-Tianjin University of Technology Project