300MW Coal-Fired Power Project at Gwadar

Project 300MW Coal-Fired Power Project at Gwadar
Primary Energy Input Coal (Imported)
Technology Super Critical
Installed Capacity (MW) 300
Location Gwadar
Province Balochistan
Estimated Cost (US $ Million) 542.32
Executing Company / Sponsors China Communications Construction Company (CCCC)
Coordinating Ministry Ministry of Energy (Power Division)
Supervising Agency Gwadar Port Authority (GPA) / Gwadar Development Authority (GDA)
Total Jobs Opportunities During the Construction of this Project 1000
Project Progress Update
  • Tariff determined in Sep 2019.
  • Land acquired in Feb 2020.
  • GoP-IA and PPA signed on 8th April 2021.
  • Financial Close (FC) under process.