| Project | 1124MW Kohala Hydropower Project, AJK |
|---|---|
| Primary Energy Input | Hydel |
| Installed Capacity (MW) | 1124 |
| Location | Jhelum River near Muzaffarabad |
| Estimated Cost (US $ Million) | 2,400 |
| Executing Company / Sponsors | CTG/CWEI (China Three Gorges) / (CWE Investment Crop) |
| Financing | Independent Power Producer (IPP) |
| Coordinating Ministry | Ministry of Energy (Power Division) |
| Supervising Agency | Private Power and Infrastructure Board (PPIB) |
| Total Jobs Opportunities During the Construction of this Project | 7500 |
| Project Progress Update |
|